Compatible with Traditional Construction Method (Bottom to Top). Apply double circumferential SAW (Submerged Arc Welding) seams simultaneously inside and outside the tank. It drives hanging on the tank’s upper edge. Input power: 120/240/1P/50/60. Included: Two Lincoln PowerPlus 1000 HD (380/480/3/50/60) with Intertek certification SPE-1000; plus, two welding head controllers and two wire feeders. Not included welding cables. Required: Two cables of 120 mm² x 60 m for welding up to 600 amps. Four cables for welding up to 800 amps. Six cables for welding up to 1000 amps.
3D AGW-2 Model Traditional Method
Specifications:
Trolley motorized speed: 200 up to 2,900 mm/minute.
Trolley manual: Quick move with clutch lever
Plate height: 1.5 to 3.0 m
Tank diameter: Minimum 8.0 m
Plate thickness: 8 to 50 mm
Weight (fixture itself): 1,360 kilos
Dimensions AGW-2: 3.10 m (L) x 2.50 m (W) x 2.65 m (H)
Dimensions power source storage box: 1.30 m (L) x 1.10 m (W) x 1.30 m (H) @ 2 units
Input Power: 120/240 V, 50/60 Hz, 1 P
Power: 0.19 kw
Warranty: One year
Included:
• Heavy-duty motorized carriage: Two units
• Control Box: Forward/Stop/Reverse/Speed Adjustment with display in mm/min
• Frequency driver.
• Wire reel for 60 lbs coil: Two units.
• One contact nozzle assembly for 3/32” (2.4 mm)
• One contact nozzle assembly for 1/8” (3.2 mm)
• One contact nozzle assembly for 5/32” (4.0 mm)
• One contact tip 3/32” (2.4 mm).
• Flux recovery & delivery system: Two sets.
• Flux belt 4” x 40”
• Flux assembly with 150 mm wheel diameter.
• Flux Hopper with 20 kilos capacity.
• Manual welding head (X-Y) cross slide with 6” stroke: Two
• Power cable 2.5 mm² *4 wires* 60 m: Two units.
• Control cable 1.5 mm² *10 wires* 60 m: Two units
• Electric control panel: One
• Power source steel storage box: Two units
• Operation Manual & Electric Diagram
• One-year Warranty
Not included:
Welding cable 120 mm² x 60 m.
Delivery Time:
Within Canada: Three to five business days
USA & US-Mexican border: One week
Latino America: Four weeks
World-Wide: Five to six weeks
Notes:
1. The user is solely responsible for certifying WPS & PQR. A professional welding engineer should design [considering the applicable Code and Standards] by selecting the essential welding parameters such as plate beveling, wire and flux specifications, amperes and voltage, welding speed, etc.
2. Rental Facility for Tank Welding Practice
Our company does not provide training; Girth Welders must be operated by an experienced submerged arc welding operator with an updated ticket. A rental facility is available to familiarize yourself with our equipment and obtain the samples needed to qualify for the Welding Procedure Specifications (WPS), Procedure Qualifications Records (PQR), and Welder Qualification Test (WQT).
• The user should provide a steel-base plate with beveling, wire and flux.
• Minimum rental of five business days in an eight-hour shift. Includes: Two AGW-1-C and one SAW Welding Tractor.
• Maximum two operators at a time and one supervisor.
• Booking: Two to four weeks in advance.
• The user is required to provide a certificate of liability insurance.